Location: On a 2 acre site 3 miles south of Ripon, CA
Technical Description: 49 MW combined-cycle and 200,000 lb/hr dual fuel cogeneration facility
Natural Gas-fired GE LM-5000 STIG 120 gas turbine
IHI Power Turbine
A 16-inch gas pipeline connects the Kern Mojave Pipeline to the facility
PPA(s): Plant sells 100% of capacity and energy to PG&E through 2018
Steam Host: Fox River Paper Company
Fuel Supply: BP Energy Company
Interconnection Agreement: PG&E